Project Opportunities

Project Opportunities

Capital projects included in NYSEG’s 2018 Capital Investment Plan (CIP) Filing that passed the NWA Screening Criteria are included below:

Transmission/Distribution

 Project Name

 Time of Need

 Estimated RFP Release Timing

Distribution

Java 2nd Transformer and 12 kV Conversion - NWA RFP in Progress

2019

Released

Transmission

New Gardenville Substation - Add 3rd 230/115 kV Transformer - NWA RFP in Progress

2021

Released

Distribution

Stillwater Substation - Upgrade Transformer to 14 MVA - NWA RFP in Progress

2022

Released

Transmission

Northside 115/34.5 kV Transformer B1 and B2 Replacement

2022

2018

Transmission

Liberty - Grossinger 34.5 kV Line 341 Upgrade

2023

TBD

Distribution

Hilldale - 115 kV Source, Transformer Bank Upgrade and Second 12 kV Distribution Circuit

2024

TBD

Distribution

Sloan - Add a Second Transformer Bank and Fourth Circuit Position

2024

TBD

Transmission

Pawling - Ten Mile River New 115 kV Line (Line 825 Rebuild)

2024

TBD

Distribution

Orchard Park - Add a 2nd Tranformer Bank

2025

TBD

Transmission

Northside - Morningside Heights 34.5 kV Line 455 Upgrade

2025

TBD

Transmission

Brainard Tap - W. Lebanon 34.5 kV Line 620 Upgrade

2025

TBD

Transmission

Cornstock - Franchise Line 34.5 kV Line 625 and Line 626 Upgrade

2025

TBD

Transmission

Coopers Corners - Maplewood - Kiamesha 34.5 kV Line 347 Upgrade

2026

TBD

Transmission

Ferndale - Liberty 34.5 kV Line 348 Upgrade

2026

TBD

Distribution

Bulkhead - Replace Transformer Bank #2

2027

TBD

Distribution

Marcellus Transformer Bank Replacement and 12 kV conversion

2027

TBD

Distribution

Crafts - Add 2nd Transformer and 4th 13.2 kV Circuit Position

2028

TBD

Distribution

Old Fall Substation - Install 2nd LTC Transformer

2029

TBD

Distribution

Sackett Lake Sub - Replace Transformer with 7.5 MVA Unit & Convert Distribution to 12.5 kV

2032

TBD

Current Projects

Java Substation
Java Substation, located in our Lancaster Division, is a 34.5-4.8 kV substation with two distribution feeder circuits that serve approximately 1,665 customers. The existing 5 MVA bank has exceeded the nameplate rating and one circuit has significant load growth. The NWA project to postpone the transformer replacement was initiated with an RFP in 2016.

Stillwater Substation
Stillwater Substation, located in our Mechanicville Division, is a 2.8 MVA substation that serves approximately 1,270 customers. The transformer at the substation is near or over its nameplate rating. The traditional wires project is to upgrade the Stillwater Substation with a new 34.5-4.8 X 12.5 kV, 10/12.5 (14) MVA, LTC transformer and convert approximately two miles of distribution circuit to 12.5 kV from the substation to Colonial Drive. An RFP requesting NWA solutions for this project was issued in July 2017.

New Gardenville Substation
The New Gardenville Substation, located in our Lancaster Division, contains two 230/115 kV transformers that have experienced low bus voltages and thermal overload. The traditional wires project is to install a third 230/115 kV transformer at the substation and operate it in parallel with the two existing transformers. An RFP requesting NWA solutions for this project was issued in September 2017.

Upcoming Projects

Northside Substation
Northside Substation, located in our Binghamton Division, is a load relief project. The traditional wires solution is to upgrade the 115/34.5 kV LTC Transformer by replacing the #2 LTC bank with a larger LTC having a summer normal rating above 70 MVA and replace the #1 Non LTC bank with a larger one having a summer LTE rating of at least 60 MVA. We plan to release an RFP requesting NWA solutions for this project in 2018.

Nodo: liferay-4:8080