Non-Wires Alternatives

Moving Toward the Interactive Grid of the Future

Non-Wires Alternatives

We are committed to considering Non-Wires Alternatives (NWA) solutions to electric capital investments where they are appropriate and cost-effective, and supporting principles from the New York Public Service Commission’s Reforming the Energy Vision (REV) regulatory framework. NWA solutions utilize third-party Distributed Energy Resources (DERs) to postpone certain traditional construction projects needed primarily to correct system overloading conditions and in some cases, system reliability issues.

Strategy

Our strategy for NWA is to build a portfolio of NWA DER projects which are cost effective for customers, provide reliable alternatives to traditional capital investment projects, and provide full cost recovery and earnings opportunities for our companies, while we comply with regulatory directives and learn from and work cooperatively with other utilities and stakeholders.

Project Selection and Process

NWA solutions provide the opportunity to improve reliability, explore alternative infrastructure solutions and contribute to New York’s energy vision. To determine upcoming distribution and transmission projects suitable for these solutions, several factors are considered. Traditional electric system construction projects that meet a need for decreased demand and/or increased reliability, with a minimum of 36 months until time of need and construction costs greater than $1,000,000 are reviewed as potential NWA projects. Projects are evaluated and ordered according to time of need. Requests for proposals (RFP) are then scheduled and reviewed to determine cost-effectiveness and technical viability.

Project Opportunities

Capital projects included in NYSEG’s 2018 Capital Investment Plan (CIP) Filing that passed the NWA Screening Criteria are included below:

Transmission /Distribution

 Project Name

 Time of Need

 Estimated RFP Release Timing

Distribution

Java 2nd Transformer and 12 kV Conversion - NWA RFP in Progress

2019

Released

Transmission

New Gardenville Substation - Add 3rd 230/115 kV Transformer - NWA RFP in Progress

2021

Released

Distribution

Stillwater Substation - Upgrade Transformer to 14 MVA - NWA RFP in Progress

2022

Released

Distribution

Lansing Non-Pipes Alternatives

2021

Released

Current Projects

Java Substation

Java Substation, located in our Lancaster Division, is a 34.5-4.8 kV substation with two distribution feeder circuits that serve approximately 1,665 customers. The existing 5 MVA bank has exceeded the nameplate rating and one circuit has significant load growth. The NWA project to postpone the transformer replacement was initiated with an RFP in 2016.

Stillwater Substation

Stillwater Substation, located in our Mechanicville Division, is a 2.8 MVA substation that serves approximately 1,270 customers. The transformer at the substation is near or over its nameplate rating. The traditional wires project is to upgrade the Stillwater Substation with a new 34.5-4.8 X 12.5 kV, 10/12.5 (14) MVA, LTC transformer and convert approximately two miles of distribution circuit to 12.5 kV from the substation to Colonial Drive. An RFP requesting NWA solutions for this project was issued in July 2017.

New Gardenville Substation

The New Gardenville Substation, located in our Lancaster Division, contains two 230/115 kV transformers that have experienced low bus voltages and thermal overload. The traditional wires project is to install a third 230/115 kV transformer at the substation and operate it in parallel with the two existing transformers. An RFP requesting NWA solutions for this project was issued in September 2017.

Lansing Non-Pipes Alternatives

The Lansing Non-Pipe Alternatives (NPA) Request for Proposal (RFP) seeks responses from qualified and experienced respondents with the capability to deliver innovative solutions that provide needed natural gas system load relief in the Lansing New York Gas Moratorium and surrounding areas. NYSEG is issuing this RFP for resources which will defer or eliminate the need for the construction of the planned Lansing/Freeville Reinforcement Gas Pipeline Project, by either or both the reduction of existing natural gas usage and/or the introduction of additional natural gas equivalent supply (in various forms of energy) into the Lansing, NY area. The NPA solution(s) must address the Companies' responsibility to provide safe and reliable service at reasonable costs and in an environmentally-sound manner.

An RFP was issued in December 2019 and relevant documents are listed below.

Associated Documents

 

Upcoming Projects

News and Updates

View news and updates on projects.

Additional Questions?

Contact us nonwiresalternatives@avangrid.com.